BHP stock targets 650,000 tonnes of copper by 2040

Published on 11/24/2026 at 09:37 | Editorial responsibility: Rafael Müller, Editor-in-Chief AD HOC NEWS
BHP stock is tied to a staged plan spanning Olympic Dam, Carrapateena and Prominent Hill. The strategy puts copper growth and project execution in focus.

BHP plans a larger copper province

  • BHP presented a staged strategy to lift Copper South Australia production to about 500,000 tonnes per year by 2035 and up to 650,000 tonnes by 2040.
  • The plan covers Olympic Dam, Carrapateena and Prominent Hill, with block caving and a two-stage smelter at its core.
  • BHP expects project decisions and construction milestones to unfold from 2027 onward, leaving execution and funding discipline central for investors.
BHP, US0886061086, Illustration mit AI erstellt.

On November 23, 2026, BHP presented a staged growth strategy for its South Australian copper business in an ASX exchange release. BHP said Copper South Australia could reach about 500,000 tonnes of annual copper production by 2035 and as much as 650,000 tonnes by 2040.

BHP stock traded at 63.75 euros on Lang & Schwarz at 09:30 CET on Tuesday, November 24, 2026.

A staged expansion across three assets

The strategy combines Olympic Dam, Carrapateena and Prominent Hill in an integrated development program. BHP presented the projects as a way to increase mine and processing capacity while using the existing infrastructure around Olympic Dam.

Block caving is central to the plan. BHP said the mining method could expand production at depth, improve scale and lower mining costs. At Carrapateena, the company is progressing a block-cave expansion with a first drawbell targeted for early fiscal 2030 and first production targeted for fiscal 2030. The project has an estimated capital requirement of 1.8 billion to 2.1 billion US dollars and an indicative internal rate of return of 19% to 22%.

At Olympic Dam, BHP is studying a larger block-cave operation and a new concentrator. The company presented an indicative capital range of 4.1 billion to 5.4 billion US dollars for the mine and concentrator growth project, with a final investment decision scheduled for calendar 2029 and first production targeted for fiscal 2034. BHP said a preferred alternative for the block cave is expected to be selected within the next 12 months.

Smelting is a key project dependency

BHP also outlined a two-stage smelter and refinery expansion. The project would add a primary flash smelting furnace and acid plant, convert the existing furnace for secondary flash converting and expand refinery capacity. BHP presented capital spending of 3.2 billion to 4.1 billion US dollars, with a final investment decision scheduled for the second half of calendar 2027 and first production targeted for fiscal 2032.

The company said the smelter expansion is needed to process the planned increase in production and make better use of Olympic Dam's resource. The presentation also linked the project to higher by-product output. BHP expects copper-equivalent production from gold, uranium and silver by-products to rise by 50% by 2035, with uranium production reaching about 6 kilotonnes per year.

Funding and execution remain central

BHP said its copper business generated positive attributable free cash flow in every year of the period shown and could produce about 35 billion US dollars of cumulative positive attributable free cash flow through 2035. For Copper South Australia Phase 1, the company presented average annual growth capital of about 1.3 billion US dollars and cumulative free cash flow to 2035 of about 9 billion US dollars under its consensus-price assumption.

The company also said it had awarded more than 3 billion US dollars of major contracts and was already executing enabling work. Projects remain at different stages of study and are subject to further study and decisions. For investors, the strategy increases BHP's copper growth option but also leaves capital discipline, approvals, water infrastructure and project delivery as important milestones.

BHP stock facts

  • Company: BHP Group Limited
  • ISIN: US0886061086
  • Lang & Schwarz quote: 63.75 euros at 09:30 CET on November 24, 2026
  • Key event: Copper South Australia site tour and growth strategy presented on November 23, 2026

The European market overview provides broader market context for investors.