NextDC stock: M3 construction update sets December schedule
Published on 11/13/2026 at 20:19 | Editorial responsibility: Rafael Müller, Editor-in-Chief AD HOC NEWSM3 work schedule and investor context
- NEXTDC scheduled generator commissioning and related construction activity at M3 Melbourne for December.
- The company cancelled the planned November 11 generator test and outlined further crane and parking work.
- Stages 1 and 2 are operating, while stages 3 and 4 remain under construction.
On November 11, NEXTDC published a new construction update for its M3 Melbourne data centre, covering December generator commissioning, crane activity and parking arrangements. The NEXTDC M3 Melbourne community update also lists additional trade-partner parking as part of the site works.
The company said the November 11 generator test was cancelled. The next planned routine maintenance is scheduled for December 4 and 9, while construction activity is set to continue through the month.
Construction milestones remain central
NEXTDC describes Stages 1 and 2 as operational. Stages 3 and 4 are under construction, with Stage 4 fit-out and commissioning underway and completion for Stage 4 expected in mid-2027. Proposed Stages 6 and 7 remain under assessment by the Victorian Government.
The near-term schedule gives investors a clearer view of the physical work planned at the Melbourne campus and the local operating activity that will accompany it. The company also says a 250-tonne crane will operate in the Stage 1 car park from November to mid-December, with staff parking temporarily moved to Stage 2.
NextDC stock traded at 6.20 euros on Lang & Schwarz at 20:13 CET on Friday, November 13, 2026.
NextDC Limited
- Company: NextDC Limited
- ISIN: AU000000NXT8
- Lang & Schwarz quote: 6.20 euros on November 13, 2026, at 20:13 CET
- M3 Melbourne: Stages 1 and 2 operational; Stages 3 and 4 under construction