Critical Metals Owns All of Tanbreez Now — Turning It Into a Mine Is the Hard Part
Published on 11/25/2026 at 04:51 | Editorial boerse-global.deCritical Metals has finished absorbing European Lithium and, with it, secured outright ownership of the Tanbreez project. The company issued roughly 90.5 million new shares to pay for the transaction, a move that lifted its share count and reshaped both its capital base and its ownership structure. What the deal did not deliver is a producing mine.
The cash position immediately after closing stood at about US$264.5 million. That figure describes the balance sheet at the moment the transaction completed — a snapshot, not a forecast. It gives Critical Metals room to keep developing Tanbreez, but the money for actual mine construction is to be raised separately.
A timetable with little slack
Management is targeting a definitive feasibility study for the fourth quarter of 2027. First ore at Tanbreez is pencilled in for late 2028 to early 2029. Both are company objectives, and the gap between them is narrow. The schedule only holds if each step follows the last without meaningful delay, leaving scant room for anything that comes after the study's planned completion.
Ownership is no longer in question. Since the November takeover, Tanbreez has belonged entirely to Critical Metals, which alone decides on mining, pace and offtake partners. The market, for its part, has handed the stock a valuation of roughly EUR 655 million — for a project that still has both a feasibility study and first production ahead of it.
Should investors sell immediately? Or is it worth buying Critical Metals?
Permits: part done, part outstanding
On the regulatory front, the company can point to one clear win. Its mining and closure plan has been approved, giving the project a legal framework. Construction, however, requires specific operating permits and a security deposit, and neither is in hand.
Technical work is where Critical Metals has advanced furthest, and that matters. In September the company reported tests in which its eudialyte concentrate dissolved to more than 99 percent. A preliminary study also exists for the planned refinery in Romania that would process the concentrate further — genuine progress on the downstream stage, since dissolution is the gateway to extracting anything sellable from the concentrate.
Industrial-scale throughput, though, has not been demonstrated. The annual report itself notes that the processing scheme has not been validated at commercial scale.
Critical Metals at a turning point? This analysis reveals what investors need to know now.
One offtake contract, a fraction of output
On the buyer side, a binding 15-year agreement with REalloys has been in place since May. It covers at most 15 percent of annual concentrate production.
Set against all this, Tanbreez remains a long way from a working mine. It lacks a bankable study, an operating licence and a large-scale proven process — and construction is unfunded. Until ore flows, the project generates no revenue from concentrate and instead consumes capital. The roughly US$264.5 million on hand buys development time; building the mine will take fresh money.