Vulcan, Energy

Vulcan Energy Kicks Off Main Construction at Landau as Lionheart Stays on Track for 2028

Published on 11/16/2026 at 16:31 | Editorial boerse-global.de
Vulcan Energy has begun civil construction at its Lionheart lithium plant in Germany, keeping its first production target for the second half of 2028 on track.
Vulcan Energy Illustration mit AI erstellt.

Vulcan Energy has moved into the civil construction phase at the commercial lithium extraction plant of its Lionheart project in Germany, a step that keeps the company's first production target of the second half of 2028 intact. The works follow extensive earthmoving on the Landau site and cover foundations, concrete structures, roads and drainage systems. Buildings and process installations are scheduled to come next.

According to the company, the build remains on schedule and on budget and meets the key milestones set for 2026. Shares nevertheless slipped 3.8% on Friday.

Extraction, processing and energy in one concept

Lionheart pairs lithium recovery with geothermal energy use, so the economics rest on more than the extraction plant alone. Heated deep brine from the Upper Rhine Graben is to yield lithium chloride first, which is then processed into battery-grade lithium hydroxide in Frankfurt-Höchst. The company is targeting up to 24,000 tonnes of lithium hydroxide monohydrate a year — an intended output, not a volume achieved to date — which it says would be enough for roughly 500,000 electric vehicle batteries.

Should investors sell immediately? Or is it worth buying Vulcan Energy?

Alongside the battery raw material, the project is designed to deliver 275 GWh of renewable electricity and 560 GWh of heat annually over an estimated 30-year operating life. The heat is to supply Landau through a district heating network, tying the venture to the local energy system as well as to the battery supply chain.

Drilling fleet expands

Work on the subsurface side is advancing in parallel. On 10 November Vulcan began relocating its second proprietary heavy-duty drilling rig, designated V10, to the Trappelberg drilling site. The rig is meant to support simultaneous execution of the Lionheart drilling programme. Vulcan has invested around €51 million in its two rigs in total — a figure that relates to the drilling equipment and not to the construction work reported today.

Funding and offtake set the frame

The financing package for Lionheart is reported in the media at around €2.2 billion, with financial close reached in May 2026. Existing take-or-pay offtake agreements add a contractual framework for sales, though they do not substitute for completion and commissioning of the facilities. Financing and offtake therefore define the perimeter; construction progress documents delivery. The decisive proof — actual production — is still outstanding, and today's announcement marks an intermediate step rather than an operating plant.

Citigroup disclosure reflects securities lending

Separately, Citigroup published a change to its reported relevant stake in Vulcan on Thursday. The mandatory disclosure attributes the change to securities lending transactions and standard market contracts in the ordinary course of business. The higher reported percentage therefore does not represent a straightforward net purchase of shares on the market and should not be read as an accumulation through exchange trading.

Ad

Vulcan Energy Stock: New Analysis - 16 November

Fresh Vulcan Energy information released. What's the impact for investors? Our latest independent report examines recent figures and market trends.

Read our updated Vulcan Energy analysis...

Disclaimer...
en | AU0000066086 | VULCAN | boerse | 70521579 |